PCCM Works Review: Plan Head 53
A Detailed Project-by-Project Analysis
Status as of June 25, 2025
Mumbai Division, Central Railway
Agenda
- High-Level Summary: Overall project status and key highlights.
- Goods Shed & Parcel Depot Modernization: Detailed review of freight and parcel infrastructure projects.
- Major Redevelopment Projects: Focus on CSMT, LTT, Lonavala, and the Amrit Bharat Station Scheme (ABSS).
- Amrit Bharat Station Scheme (ABSS) - Deep Dive: Project-wise status for all 15 ABSS stations.
- General Passenger Amenities: Progress on FOBs, Lifts, Platforms, and other key works.
- Project Pipeline & Closure: Review of new works, deletions, and short closures.
- Conclusion & Way Forward.
Overall Project Status - A Snapshot
A total of 177 works are sanctioned under Plan Head 53, indicating a massive investment in customer amenities. The portfolio is dynamic, with numerous projects at every stage of the lifecycle.
| Status | No. of Works | Percentage | Remarks |
|---|---|---|---|
| Physically Completed | 47 | 26% | 9 of these are under process for final deletion. |
| Work in Progress | 79 | 45% | Includes major ongoing schemes like ABSS and CSMT upgrade. |
| LOA Issued | 3 | 2% | Contracts awarded, work to commence. |
| Tender Stage | 4 | 2% | Includes TC Process (2) and Tender Floated (2). |
| Approval Stage | 4 | 2% | GAD (General Arrangement Drawings) under approval. |
| Estimation Stage | 40 | 23% | Includes Vetting (14) and Preparation (26). |
| Total | 177 | 100% |
Key Strategic Pillars
Our efforts are concentrated on three strategic pillars to deliver a transformational impact on passenger and freight customer experience.
1. World-Class Hub Development
CSMT Major Upgradation: A landmark project to redevelop CSMT into a global standard terminal.
Cost: ₹1,813 Cr.
Executing Agency: RLDA
2. Amrit Bharat Station Scheme
A comprehensive scheme for the modernization of 15 key stations across the division with a focus on holistic development.
Scope: Buildings, platforms, FOBs, lifts, escalators, and aesthetics.
3. Freight Infrastructure Modernization
Targeted upgrades of Goods Sheds and Parcel Depots to improve efficiency, capacity, and amenities.
Key Locations: Kalyan, LTT, Turbhe, Nagothane, Taloja.
Section 2
Goods Shed & Parcel Depot Modernization
Enhancing Freight and Parcel Handling Capabilities
Goods Shed Program - Overview
Significant investments are being made to upgrade infrastructure at key goods sheds under the PWP 2022-23 & 2023-24 programs.
| Location | Estimated Cost (₹ Cr) | Status |
|---|---|---|
| Kalyan (KYN) | 23.05 | TC Process |
| Turbhe (TAPG) | 13.28 | Work in Progress |
| Nagothane (NGTN) | 10.67 | Work in Progress |
| Taloja (TPND) | 7.99 + 17.65 | WIP / Estimation |
| Trombay (TMBY) | 34.05 | Sanctioned |
| New Mulund (NGSM) | 30.35 | Proposal with Rly. Board |
| Bhiwandi Road (BIRD) | 33.34 | Proposal with Rly. Board |
| General Lighting | 4.99 | Work in Progress |
| CCTVs | 6.75 | Sanctioned |
Goods Shed - Kalyan (KYN)
- Project Name: Improvement of Goods Shed at Kalyan (KYN)
- Estimated Cost: ₹23.05 Crores
- Sanctioned: December 13, 2024
- Scope of Works:
- Improvement of covered shed area (COP, side walls, platform resurfacing).
- Provision of new covered shed for 23 wagons.
- Improvement of circulating area and approach road with cement concreting.
- Reconstruction of culvert and improvement of drainage.
- New G+1 building for Labour/Merchant rooms.
- Provision of water sprinklers, dust screens, CCTVs.
- Current Status: Tender Opened on May 13, 2025. TC Minutes are under process.
- Executing Agency: GSU / BB
Goods Shed - Turbhe (TAPG)
- Project Name: Improvement of Goods Shed at Turbhe (TAPG)
- Project ID: 01.02.53.23.1.55.036
- Anticipated Cost: ₹14.98 Crores
- Status: Work in Progress (30% complete)
- Scope of Works:
- Provision for full-length BCNHL rake by relocating rooms.
- Replacement of old COP, valley gutters, and down-take pipes.
- Resurfacing of platform.
- New G+1 building for Labour/Merchant rooms with amenities.
- Improvement of drainage system.
- Remarks: LOA issued on September 23, 2024. Work is progressing. TDC: Dec 31, 2025.
Goods Shed - Nagothane (NGTN)
- Project Name: Improvement of Goods Shed at Nagothane (NGTN)
- Project ID: 01.02.53.23.1.55.037
- Anticipated Cost: ₹12.04 Crores
- Status: Work in Progress (25% complete)
- Scope of Works:
- Improvement of approach road and circulating area with cement concreting.
- Provision of new G+1 building for Labour/Merchant rooms.
- Provision of stacking shed.
- Enhanced drinking water and bathing facilities.
- Remarks: LOA issued on September 23, 2024. Work is progressing. TDC: Dec 31, 2025.
Goods Shed - Taloja Panchanand (TPND)
Project 1: Full Length COP
- Project ID: 01.02.53.22.1.51.006
- Cost: ₹7.99 Crores
- Status: Work in Progress (90% complete)
- Scope: Provision of full-length COP on high-level platform & drainage system.
- Remarks: Erection of COP shed is in progress. TDC: June 30, 2025.
Project 2: Additional Line & Relocation
- Project ID: 01.02.53.24.3.51.019
- Cost: ₹17.51 Crores (Est.)
- Status: Under Finance Vetting
- Scope: 700m additional line, relocation of office to new G+2 building.
Goods Shed - Trombay (TMBY)
- Project Name: Improvement of Goods Shed at Trombay (TMBY)
- Project ID: 01.02.53.24.1.51.002
- Estimated Cost: ₹34.05 Crores
- Sanctioned: May 16, 2025
- Scope of Works:
- Extension of existing handling line (from 500m to 725m).
- Extension of existing sick line (from 225m to 725m).
- Provision of a new high-level platform (700m x 20m) with COP.
- Provision of a new G+1 building (40m x 30m) for offices and rooms.
- Current Status: Sanctioned. Detailed estimate is under preparation.
- Executing Agency: Open Line
Goods Shed - Proposals with Railway Board
New Mulund (NGSM)
- Estimated Cost: ₹30.35 Crores
- Proposed Scope: Major improvements to approach road, circulating area, platforms, drainage, and COP. Includes provision for new offices and amenities.
- Status: At Railway Board for sanctioning.
Bhiwandi Road (BIRD)
- Estimated Cost: ₹33.34 Crores
- Proposed Scope: New approach roads, a G+2 service building, parcel stacking shed, and retaining walls.
- Status: Proposal with Railway Board since March 15, 2025. Remarks on queries are being prepared.
Goods Shed - General Amenity Works
Project: Improved Lighting
- Project ID: 01.02.53.23.1.55.034
- Cost: ₹4.99 Crores
- Status: Work in Progress (10% complete)
- Scope: Improvement of goods shed and yard lighting by providing additional high mast towers and indoor LED fittings.
- Remarks: Tender awarded on Nov 14, 2024. Material mobilization is in progress.
Project: CCTVs
- Project ID: 01.02.53.24.3.51.025
- Cost: ₹6.75 Crores
- Status: Sanctioned, estimate under preparation.
- Scope: Provision of 198 CCTVs at 11 Goods Sheds and 6 Parcel Depots.
Parcel Depot Program - Overview
Lokmanya Tilak Terminus (LTT)
- Project: Construction of 3 Big Warehouses
- Cost: ₹17.83 Crores
- Status: Under Finance Vetting
Wadi Bunder (WB)
- Project: Provision of Parcel Siding Platform
- Cost: ₹14.54 Crores
- Status: Under Finance Vetting
LTT, Panvel, Wadi Bunder
- Project: Parcel Management System (PMS)
- Status: PMS at LTT (Ph-II) & Wadi Bunder (Ph-III) are awarded. PMS at Panvel (Ph-I) is complete.
Parcel Depot - Lokmanya Tilak Terminus (LTT)
- Project Name: Construction of Big Warehouses with cement concreting flooring
- Project ID: 01.02.53.24.3.51.010
- Estimated Cost: ₹19.50 Crores
- Scope: Construction of 3 warehouses with a total approximate size of 7550 Sqm.
- Current Status: Sanctioned by GM on March 31, 2025. The detailed estimate is under preparation.
- Executing Agency: Open Line / BB
Parcel Depot - Wadi Bunder (WB)
- Project Name: Provision of parcel siding rail level platform
- Project ID: 01.02.53.24.3.51.018
- Estimated Cost: ₹14.54 Crores
- Scope:
- Provision of a parcel siding platform (200m x 15m).
- Cemented circulating area (200m x 20m).
- Pathway across and between stabling lines.
- Current Status: Sanctioned by GM on March 31, 2025. The detailed estimate is under finance vetting.
- Executing Agency: GSU / BB
Section 3
Major Redevelopment & ABSS
Transforming Stations into City Centres
CSMT Major Upgradation
- Project Name: Major upgradation of Chhatrapati Shivaji Maharaj Terminus (CSMT)
- Project ID: 01.02.53.23.1.84.031
- Anticipated Cost: ₹1,813 Crores
- Executing Agency: RLDA
- Status: Work in Progress (2% complete)
- Key Milestones:
- EPC Contract Awarded: April 28, 2023 (to M/s Ahluwalia Contracts).
- Contract Agreement Signed: June 1, 2023.
- PMS Appointed: July 6, 2023 (SYSTRA-MACE).
- Appointed Date Declared: July 10, 2023.
- Current Activity: 32 structural assessments are in progress.
LTT & Lonavala Redevelopment - Consultancy
- Project Name: Appointment of technical consultant for Techno-Economic feasibility studies and Master Planning for redevelopment of LTT & Lonavala stations.
- Project ID: 01.02.53.22.3.55.001
- Cost: ₹1.79 Crores
- Status: Work in Progress (50% complete)
- LTT Status:
- Consultancy contract awarded on Oct 3, 2022.
- The master plan has been approved by GM and sent to the Railway Board on May 11, 2023. Awaiting a presentation date.
- Lonavala Status:
- Booklet (KD3) submitted.
- GM has instructed to prune down the cost after reviewing the master plan concepts.
Amrit Bharat Station Scheme (ABSS) - Overview
Modernization of 15 stations is underway in Mumbai Division under ABSS, with a focus on improved amenities, accessibility, and aesthetics.
| Station Category | Names of Stations |
|---|---|
| Phase 1 | Byculla, Chinchpokli, Parel, Matunga, Kurla, Vidyavihar, Vikhroli, Kanjurmarg, Mumbra, Diva, Shahad, Titwala, Igatpuri, Wadala Road, Sandhurst Road. |
Key Project Components:
- Station Building Upgrades & Facade Improvements
- New Foot Over Bridges (FOBs)
- Provision of Lifts & Escalators
- Platform Improvements (Flooring, Shelters)
- Improved Signage, Toilets, and Waiting Areas
- Horticulture & Vertical Gardens
- Provision of Sewage Treatment Plants (STPs)
ABSS - Station Buildings (Group 1 - Completed)
Parel (LB-1943):
Cost: ₹8.58 Cr | Status: 100% complete.
Vadala Road (LB-1963):
Cost: ₹8.04 Cr | Status: 100% complete.
Matunga (LB-1961):
Cost: ₹5.34 Cr | Status: 100% complete.
Chinchpokli (LB-1959):
Cost: ₹6.44 Cr | Status: 100% complete.
Byculla (LB-1958):
Cost: ₹11.82 Cr | Status: 100% complete.
ABSS - Station Buildings (Group 2 - WIP)
Vikhroli (LB-1964):
Cost: ₹10.55 Cr | Status: 85% complete.
Remarks: New facade, service building finishing, and parking work in progress.
Diva (LB-1960):
Cost: ₹18.62 Cr | Status: 80% complete.
Remarks: Work on west side toilet block and new service building is in progress.
Sandhurst Road (LB-1962):
Cost: ₹10.37 Cr | Status: 70% complete.
Remarks: False ceiling work and extension of elevated booking office in progress.
Mumbra (LB-1957):
Cost: ₹8.70 Cr | Status: 71% complete.
Remarks: Column erection for passage and facade is in progress.
ABSS - Station Buildings (Group 3 - WIP)
Kanjurmarg (LB-1950):
Cost: ₹4.96 Cr | Status: 95% complete.
Remarks: West side circulating area and service building work in progress.
Vidyavihar (LB-1965):
Cost: ₹7.28 Cr | Status: 60% complete.
Remarks: Work on home platform and new drain is in progress.
IGP, CLA, TLA, SHAD (LB-1967):
Cost: ₹24.97 Cr | Status: 55% complete overall.
Breakdown: Igatpuri (60%), Kurla (85%), Shahad (100%), Titwala (96%).
ABSS - Foot Over Bridges (FOBs) - Part 1
Byculla FOB (LB-1940):
Cost: ₹11.33 Cr | Status: 30% complete.
Remarks: Column erection completed. Girder fabrication completed and splicing is in progress at site. TDC: June 30, 2025.
Kanjurmarg FOB (LB-1942):
Cost: ₹12.68 Cr | Status: 20% complete.
Remarks: Column erection is in progress. Girder material is under procurement. TDC: Aug 31, 2025.
Vidyavihar FOB (LB-1937):
Cost: ₹12.24 Cr | Status: 10% complete.
Remarks: Column erection is in progress. Girder material is under procurement. TDC: Sep 30, 2025.
ABSS - Foot Over Bridges (FOBs) - Part 2
Titwala FOB (LB-1941):
Cost: ₹10.31 Cr | Status: 2% complete.
Remarks: GAD approved. Foundation work yet to start. Material under procurement. TDC: Dec 31, 2025.
Diva FOB (LB-1966):
Cost: ₹16.77 Cr | Status: 5% complete.
Remarks: Piling work for foundation is 75/162 complete. Column and girder fabrication yet to start. TDC: Feb 28, 2026.
Chinchpokli FOB & Roof Plaza (LB-1970):
Cost: ₹40.16 Cr | Status: 0% complete.
Remarks: Detailed estimate vetted. Tender under preparation.
ABSS - Lifts & Escalators
Lifts (Sugamya Bharat Abhiyan Ph-II) (LB-1952):
Cost: ₹14.30 Cr
Status: LOA Issued.
Remarks: LOA issued on March 3, 2025, for 20 Lifts. Work has not yet started.
Escalators (LB-1955):
Cost: ₹48.05 Cr
Status: TC Proceedings under process.
Remarks: Tender for 30 escalators was re-invited. Financial Bid opened on March 13, 2025. TCP is under process.
ABSS - Toilets & STPs
Project 1: Toilets at VVH, VK, KJM, MBQ, DW (LB-1944):
Cost: ₹6.52 Cr | Status: 60% complete.
Remarks: Toilets completed at VVH, VK, and MBQ. Work in progress at KJM and DW.
Project 2: Toilets at TLA, SHD, IGP, VDLR, SNRD (LB-1945):
Cost: ₹6.06 Cr | Status: 100% complete.
Project 3: Toilets at BY, CHG, MTN, CLA, PR (LB-1946):
Cost: ₹6.00 Cr | Status: 100% complete.
Project 4: Provision of 25 STPs at 15 Stations (LB-1936):
Cost: ₹7.05 Cr | Status: 85% complete.
Remarks: STPs completed at 13 locations. Work in progress at Diva.
ABSS - Telecom & Electrical Works
| Project | Cost (₹ Cr) | Status | TDC |
|---|---|---|---|
| Passenger Information System (Video) (LB-1953) | 7.30 | 56% complete | July 31, 2025 |
| Public Announcement System (LB-1954) | 6.15 | 56% complete | July 31, 2025 |
| Telecom Assets & Backbone Connectivity (LB-1968) | 9.00 | 78% complete | - |
| Cable Trays & Ventilation System (LB-1951) | 6.99 | 50% complete | Aug 31, 2025 |
| Signage (LB-1956) | 3.04 | 50% complete | Aug 31, 2025 |
ABSS - Horticulture & Divyangjan Facilities
Horticulture (Group 1: SNRD, VDLR, PR, MTN, CLA) (LB-1938):
Cost: ₹5.80 Cr | Status: 50% complete.
Remarks: Vertical gardens completed at Parel, VDLR, Matunga. Work in progress at Kurla.
Horticulture (Group 2: 10 other stations) (LB-1939):
Cost: ₹9.85 Cr | Status: 50% complete.
Remarks: Work completed at Byculla and Chinchpokli. In progress at others.
Flooring for Divyangjan (LB-1969):
Cost: ₹11.83 Cr | Status: 70% complete.
Remarks: Flooring work is in progress at all 15 stations.
Section 4
General Passenger Amenities
Progress on FOBs, Lifts, Platforms, and Other Works
Legacy FOBs (2015-18 Sanctions) - Mostly Complete
Multiple FOB projects sanctioned prior to ABSS are now complete, significantly improving station accessibility.
- Masjid FOB (2015-16): 100% complete.
- Neral FOB (2015-16): 100% complete. Proposed for deletion.
- LTT FOB (2016-17): 100% complete.
- MRVC FOBs at 12 Stations (2017-18): 84% complete. FOBs at 10 stations are finished. Dadar GAD is under approval; Ulhasnagar work is pending.
- FOBs at Kalva, Diva, Dombivali, Thakurli (2018-19): 100% complete.
- FOBs at Ambernath, Shelu, etc. (2018-19): 100% complete, proposed for short closure as Ambernath FOB was handed over to MRVC.
Ongoing FOBs & FOB Improvement Works
| Project | Cost (₹ Cr) | Status | TDC |
|---|---|---|---|
| Somathane & Jite FOBs (LB-1923) | 3.64 | 2% complete | June 30, 2026 |
| Khandala FOB Replacement (LB-1930) | 3.11 | 75% complete | Dec 31, 2025 |
| FOB Roofing/Surface Improvement (BY-KOPR Sec) (LB-1924) | 4.31 | 49% complete | Dec 31, 2025 |
| Igatpuri FOB Extension (LB-2163) | 4.59 | 0% complete | June 30, 2026 |
Dadar Station - Multiple Improvement Works
Dadar station is seeing a cluster of targeted improvement works to de-congest and improve amenities.
| Project ID | Short Description | Cost (₹ Cr) | Status | TDC |
|---|---|---|---|---|
| LB-1971 | Widening of PF No.1/2. | 2.39 | 100% | Completed |
| LB-1976 | Modification of stairs/ramps on PF 5. | 2.40 | 100% | Completed |
| LB-1972 | Relocation of GRP office on PF 3/4. | 2.38 | 85% | 31-Dec-25 |
| LB-1973 | Relocation of overhead offices on PF 3/4. | 2.39 | 79% | 31-Dec-25 |
| LB-1982 | COP at additional width of PF1/2. | 2.44 | 85% | 31-May-26 |
| LB-1983 | COP at uncovered portion on PF 5. | 1.99 | 71% | 31-Dec-25 |
| LB-1975 | Extension of existing lattice FOB. | 2.47 | 0% | 31-May-26 |
Platform Improvements - Raising & Resurfacing
- Project: Raising/resurfacing of PFs at Dadar, Govandi, Bhandup, Thane, etc. (LB-1934)
Cost: ₹3.13 Cr | Status: 62% complete | TDC: Dec 31, 2025. - Project: Improvement to platform surface at Kalyan (PF 1, 1A, 2/3, 6/7) (LB-1989)
Cost: ₹2.30 Cr | Status: 35% complete | TDC: Dec 31, 2025. - Project: Improvement to platform surfacing at Ghatkopar (PF 1, 2/3, 4) (LB-1978)
Cost: ₹1.79 Cr | Status: 61% complete | TDC: Dec 31, 2025.
Platform Improvements - Cover Over Platform (COP)
| Project | Cost (₹ Cr) | Status | TDC |
|---|---|---|---|
| Improvement to COP at Dombivali (PF 5 & 3/4) (LB-1984) | 2.15 | 92% complete | June 30, 2025 |
| Improvement to COP at Bhandup (PF 1, 2/3, 4) (LB-1986) | 2.02 | 85% complete | July 31, 2025 |
| Improvement to COP at Mulund (PF 1, 2/3, 4) (LB-1987) | 2.23 | 70% complete | Dec 31, 2025 |
| Improvement to COP at Thane (PF 1, 2, 3/4) (LB-1985) | 2.35 | 80% complete | Dec 31, 2025 |
| COP at Lonavala extended portion (PF 1) (LB-1990) | 2.48 | 75% complete | June 30, 2025 |
Platform Improvements - Other Works
- Kopar - Provision of home PF (LB-1892): Cost: ₹10.11 Cr | Status: 100% complete. Proposed for deletion.
- Nahur - Provision of Home platform (LB-1922): Cost: ₹6.96 Cr | Status: 42% complete. | TDC: March 31, 2026.
- Bhiwandi Road - Extension of PF 2/3 (LB-1921): Cost: ₹5.45 Cr | Status: 100% complete.
- Kurla - Extension of PFs 3/4, 5/6, 7/8 (LB-1977): Cost: ₹2.42 Cr | Status: 20% complete. | TDC: Dec 31, 2025.
Lifts (Non-ABSS)
Project: Provision of 52 nos. Lifts (Central Railway) (LB-1905)
Sanction Year: 2018-19
Cost: ₹24.56 Cr
Status: 12% complete.
Remarks: Zonal work. HQ to comment on division-specific progress.
Project: Provision of 77 nos. Lifts (Central Railway) (LB-1904)
Sanction Year: 2018-19
Cost: ₹36.42 Cr
Status: 60% complete.
Remarks: Mumbai Division: 41 of 65 lifts commissioned.
Emergency Medical Rooms (EMRs)
- Project: EMR at 8 stations (Bhandup, Kalwa, etc.) (2016-17): Cost: ₹0.99 Cr | Status: 100% complete.
- Project: EMR at 5 stations (Byculla, Sion, etc.) (2016-17): Cost: ₹0.63 Cr | Status: 100% complete.
- Project: EMR at 24 stations (CSMT, Parel, etc.) (LB-1893): Cost: ₹4.59 Cr | Status: 17% complete. | Remarks: Contract terminated. Estimate under revision. Proposed for short closure.
Water Supply & Water Tank Works
- Igatpuri Station Water Supply (LB-1913): Cost: ₹1.37 Cr | Status: 35% complete. TDC: March 31, 2026.
- Water Facilities at KJT-KHPI & PNVL-KJT sections (LB-1925): Cost: ₹3.69 Cr | Status: 92% complete. TDC: Dec 31, 2025.
- Replacement of Unsafe Water Tanks (New Works 2023-24):
- CSMT (NAB/Annex Bldg): 78% complete.
- Kurla Diesel Shed: 19% complete.
- LTT: 40% complete.
- Kurla Carshed: 41% complete.
Ballastless Track & Washable Apron Works (New)
| Project | Cost (₹ Cr) | Status |
|---|---|---|
| Ballastless Track at Panvel (PF 5, 6, 7) (2024-25) | 14.65 | Under Finance Vetting |
| Washable Apron / BLT at CSMT (PF 8, 9, 15, 16) (2024-25) | 18.56 | Estimate under preparation |
| Washable Apron / BLT at Dadar (PF 13, 14) (2024-25) | 7.64 | Estimate under preparation |
| Washable Apron / BLT at LTT (PF 1, 2, 3) (2024-25) | 19.01 | Estimate under preparation |
| Ballastless Track at Dadar, Kurla, Thane, Dombivli (2024-25) | 15.10 | Estimate under preparation |
Train Management System (TMS) - A Major Upcoming Initiative
Seven new works have been sanctioned in the 2024-25 budget for the provision of TMS and associated station equipment across various sections of Mumbai Division.
| Section | Estimated Cost (₹ Cr) |
|---|---|
| CSMT - PNVL | 18.73 |
| TNA - KYN | 17.38 |
| Trans Harbour & BEPR - Uran | 15.18 |
| CSMT - MTN | 19.31 |
| Sion - TNA | 18.62 |
| KYN - LNL | 19.50 |
| KYN - IGP | 18.90 |
| Total Cost | ₹127.62 Crores |
Current Status: Detailed Estimates for all seven works are under preparation.
WIP Deep Dive - Chikhloli Station Construction
Project 1: Platform, COP, FOB, Track Works (LB-1907)
Cost: ₹10.02 Cr | Status: 11% complete.
Project 2: Station Bldg, Booking Office, Water Supply (LB-1908)
Cost: ₹5.94 Cr | Status: 9% complete.
Executing Agency: MRVC (as part of MUTP-IIIA)
Remarks: Land acquisition is complete. The main contract has been awarded, and work is in its initial stages.
Target Completion Date (TDC): December 31, 2026.
WIP Deep Dive - Kalyan Indicators (LB-1910)
- Project Name: Kalyan: Replacement of suburban indicators and Coach Guidance display Boards with graphical type LED display based on RDSO Spec.
- Cost: ₹2.96 Cr
- Status: 65% complete
- Agency: S&T
- Remarks: 90% installation work is complete. Some material like HDPE pipe, NVR IP camera, modem, router etc. are pending for supply. Some installation issues to be resolved.
- TDC: May 31, 2025
WIP Deep Dive - Atgaon Elevated Booking Office
- Project ID: 01.02.53.21.4.51.007
- Project Name: Atgaon-Provision of Elevated Booking Office at Atgaon station.
- Cost: ₹0.39 Cr
- Status: 16% complete
- Agency: Engineering
- Remarks: Contract awarded. Scope includes new elevated booking office on UP line side and dismantling of old booking office. Foundation excavation Work completed. Structural design approval is in progress.
- TDC: December 31, 2025
WIP Deep Dive - Lonavala Station Upgradation (DN Side)
- Project ID: 01.02.53.22.1.51.002
- Project Name: Lonavla:- Upgradation of Lonavla station on DN side by development circulating area, approach road and parking area etc.
- Cost: ₹3.49 Cr
- Status: 99% complete
- Agency: Gati Shakti Unit (GSU)
- Remarks: Work is physically complete. Final bill is under preparation.
- TDC: Completed
WIP Deep Dive - Nahur Home Platform
- Project ID: 01.02.53.22.1.51.011
- Project Name: Nahur (SG-2): Provision of Home platform
- Cost: ₹6.96 Cr
- Status: 42% complete
- Agency: Engineering
- Remarks: Platform coping wall completed. RCC flooring, RCC walling & COP columns erection is in progress.
- TDC: March 31, 2026
WIP Deep Dive - Improvement to Circulating Area
- Project ID: 01.02.53.22.1.51.003
- Project Name: Improvement to circulating area & road from Chhatrapati Shivaji Maharaj Terminus to Kalyan & King Circle to Mankhurd Stations.
- Cost: ₹14.15 Cr
- Status: 95% complete
- Agency: R (RLDA/MRVC)
- Remarks: Work completed at Chunabhatti, Mankhurd, LTT, Mulund, Thane, Kopar, Thakurli & Kalyan. Further work is in progress.
- TDC: June 30, 2025
WIP Deep Dive - FOB Roofing System Improvement
- Project ID: 01.02.53.22.1.51.008
- Project Name: BY–KOPR Sec. :- Impro. of roofing system and surface of FOB’s including addl./impr./reconstr. to staircase.
- Cost: ₹4.31 Cr
- Status: 49% complete
- Agency: Engineering
- Remarks: Strengthening of FOB staircase completed at Mulund PF-1, Vikhroli, Ghatkopar & Matunga. Further strengthening of staircase is in progress at Parel, Chinchpokali, Mulund PF-2/3.
- TDC: December 31, 2025
WIP Deep Dive - Architectural Consultancy for ABSS
- Project ID: 01.02.53.22.3.55.004
- Project Name: Architectural consultancy for 15 Railway station of Mumbai division in Amrit Bharat Station Scheme.
- Cost: ₹1.68 Cr
- Status: 90% complete
- Agency: Gati Shakti Unit (GSU)
- Remarks: Architectural consultancy for all 15 Railway stations have been awarded. Plans for all 15 stations of ABSS finalised and approved by DRM. Work in progress.
- TDC: June 30, 2025
WIP Deep Dive - Dadar GRP Office Relocation
- Project ID: 01.02.53.23.3.51.015
- Project Name: Dadar (NSG 1) :– Relocation of existing GRP office on PF 3/4 for de-congestion at CSTM end.
- Cost: ₹2.38 Cr
- Status: 85% complete
- Agency: Engineering
- Remarks: Detailed estimate sanctioned. Construction of new GRP office on PF-6 is in progress.
- TDC: December 31, 2025
WIP Deep Dive - Lonavala COP Extension
- Project ID: 01.02.53.23.3.51.022
- Project Name: Lonavla (NSG 3): - Provision of COP on extended portion of PF 1 (190 M) and other passenger amenities at PA end.
- Cost: ₹2.48 Cr
- Status: 75% complete
- Agency: Engineering
- Remarks: Foundation and columns erection completed. Roofing work is in progress.
- TDC: June 30, 2025
Section 5
Project Pipeline, Closures & Deletions
Streamlining the Project Portfolio
Works Proposed for Deletion
10 works are proposed for deletion. These projects are 100% physically complete, and their final bills have been passed. This is a crucial administrative step to clean the records.
| SN | Sanction Year | Short Name of Work |
|---|---|---|
| 1 | 2015-16 | Neral FOB Replacement |
| 2 | 2018-19 | KOPAR - Provision of home PF |
| 3 | 2018-19 | Thane - Addl. floor on parking structure |
| 4 | 2018-19 | Nilje/NGTN/PEN - Office Improvements |
| 5 | 2022-23 | Kalyan - PF shelter on dismantled portion |
| 6 | 2022-23 | Launching of ‘One Station One Product’ Scheme |
| 7 | 2022-23 | Improvement of booking/parcel/goods office furniture |
| 8 | 2021-22 | Kalyan - Mainline indicators |
| 9 | 2021-22 | Improvement of Divyangjan facility (audio beeper) |
| 10 | 2021-22 | Augmentation of IP based Central Announcement system |
Works Proposed for Short Closure
5 key works are proposed for short closure. This occurs when the full scope is no longer required, often because it has been merged with a larger, newer project.
- New Booking Offices (LB-1888): Reason: Work at Currey Road & Karjat dropped due to site unavailability.
- Emergency Medical Rooms at 24 stations (LB-1893): Reason: Contract terminated for slow progress. The remaining work will be done under a revised estimate/new tender.
- FOB at Khadavali, etc. (LB-1895): Reason: FOB at Khadavali will now be done by the Construction Organization as part of the 3rd & 4th line project.
- FOB at Ambernath, etc. (LB-1896): Reason: Ambernath FOB is now part of the MRVC 3rd & 4th line project.
- Provision of TC Office (2021-22): Reason: Scope at most stations is now covered under ABSS works.
The New Works Pipeline - At Estimation Stage
A strong pipeline of 40 new projects ensures continuous development. These are currently in the estimation or finance vetting stage.
| Status | No. of Works | Key Projects Include |
|---|---|---|
| Under Finance Vetting | 14 | Parcel Depots (WB), Goods Shed (TPND), Ballastless Track (Panvel), Multi-level parking (Dombivali), ABSS Ph-II works (Panvel, Thakurli) |
| Under Preparation | 26 | TMS (7 works), Washable Aprons (CSMT, DR, LTT), Goods Shed (Trombay), New COPs, Station Upgrades (Karjat, Roha) |
The New Works Pipeline - At Tender/Approval Stage
11 works have moved beyond estimation and are in advanced pre-execution stages.
| Status | No. of Works | Key Projects Include |
|---|---|---|
| LOA Issued | 3 | Lifts (ABSS), Information Boards, Drinking water booths. |
| TC Proceedings / Tender Floated | 4 | Kalyan Goods Shed, Escalators (ABSS), CSMT Indicators, Dadar Ramp. |
| GAD under Approval | 4 | FOBs at Somathane, Jite, Dadar, Igatpuri; Chinchpokli ABSS work. |
Financial Allocation Summary
Financial Snapshot - Key Allocations (Figures in ₹ Lakhs)
| Project Name | Original Cost | Anticipated Cost | Expenditure Upto Date | Outlay 2025-26 | Balance |
|---|---|---|---|---|---|
| CSMT Upgradation | 18,13,000 | 18,13,000 | 4,91,490 | 4,00,000 | 9,41,830 |
| MRVC FOBs (12 Stns) | 1,34,360 | 1,37,360 | 1,26,520 | 10,000 | 839 |
| ABSS Escalators | 48,050 | 47,575 | 3,601 | 2,000 | 42,189 |
| ABSS Lifts | 14,300 | 14,290 | 153 | 5,000 | 9,173 |
| Kalyan Goods Shed | 23,050 | 23,050 | 0 | 500 | 22,550 |
| Turbhe Goods Shed | 13,279 | 14,979 | 4,476 | 900 | 14,073 |
Section 6
Conclusion
Key Achievements
- Significant Completions: 47 projects are physically complete, directly benefiting passengers and freight customers.
- ABSS Momentum: The Amrit Bharat Station Scheme is well underway, with 5 stations already completed and many others in advanced stages, promising a visible transformation.
- Strategic Project Initiation: Landmark projects like the CSMT redevelopment have been successfully launched.
- Portfolio Management: Proactive steps are being taken to clean up records by proposing the deletion and short closure of legacy projects.
- Robust Pipeline: A healthy pipeline of 40 new works ensures that the pace of development will continue.
Way Forward - Key Focus Areas
- Expedite High-Impact Projects:
- Closely monitor the CSMT Redevelopment project to ensure milestones are met.
- Prioritize the tendering and awarding of contracts for the remaining ABSS works, especially escalators.
- Accelerate the execution of Goods Shed projects at Kalyan, Turbhe, and Nagothane.
- Resolve Bottlenecks in WIP:
- Address the issues leading to the termination of contracts for EMRs and Booking Offices and ensure swift re-tendering.
- Follow up on GAD approvals for critical FOBs to move them into the execution phase.
- Streamline New Projects:
- Fast-track the estimate preparation and vetting for the 40 new works, especially the Train Management System (TMS) projects.
- Administrative Efficiency:
- Complete the process of deleting and short-closing all identified works to ensure accurate reporting and financial management.